Edge Router Upgrade - B Side - Singapore

Scheduled Maintenance Report for Linode

Completed

The scheduled maintenance has been completed.
Posted Apr 28, 2017 - 04:45 UTC

Update

This maintenance has been extended to 0445 UTC.
Posted Apr 28, 2017 - 02:39 UTC

Update

This maintenance has been extended by 2 hours.
Posted Apr 27, 2017 - 22:55 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 27, 2017 - 20:00 UTC

Update

This maintenance will commence 24 hours later than originally planned.
Posted Apr 26, 2017 - 07:41 UTC

Scheduled

On Wednesday, April 26, at 8pm UTC, our engineers will be performing an edge router upgrade in our Singapore datacenter. We will be working exclusively on the "B" side of the network, and do not expect any downtime during this maintenance as we have full redundancy. However, brief periods of packet loss or increased latency may be observed at times. We expect this maintenance to take 4 hours.
Posted Apr 11, 2017 - 14:36 UTC
This scheduled maintenance affected: Regions (AP-South (Singapore)).